Route 17 (Marsh Road), Fauquier County
Upcoming Schedule
The following small bridge and structure rehabilitation projects are planned through Dec. 2021. Projects will be scheduled according to priority as weather and resources allow. Estimated construction months are subject to change.
County | Bridge | Schedule |
Albemarle | Route 810 (Blackwells Hollow Road) over Rocky Bar Branch | Oct.-Nov. |
Louisa | Route 640 (East Jack Jouett Road) over Foster Creek | Oct.-Nov. |
More Information
For more information about Virginia’s bridges and VDOT’s bridge inspection program, including current conditions of the state’s bridges, FAQs and video of a bridge inspection, visit www.virginiadot.org/info/Bridge.asp.
Benefits
The small bridge program rehabilitates aging bridges that serve county residents. If not replaced, the existing bridges will continue to deteriorate and would eventually have to be closed to vehicular traffic.
Resources
Glenn McAninch
(540) 829-7638
Phase: Under construction
Lat/Long: 38.460203, -77.997764