Project at a Glance
Begin Date
September 2013

Est Completion Date
December 2013

Phase
Study

Locality
Fredericksburg, Spotsylvania, and Stafford

District
Fredericksburg

Contact
Kelly Hannon, VDOT Communications Manager
(540) 374-3344

Study Description

In September 2013, Virginia Secretary of Transportation Sean Connaughton asked VDOT to make a recommendation for congestion relief in the Fredericksburg area at Interstate 95, Route 17 and Route 3 near the Rappahannock River. Secretary Connaughton made this request at the September 17-18, 2013 CTB meeting and workshop held in Fredericksburg. 

Before VDOT undertakes any project, it has to determine the project’s purpose and need. For this study, the purpose was to reduce congestion by identifying alternatives that improve traffic operations and assist the flow of commerce along I-95, Route 17 and Route 3. The need was identified as reducing current and future congestion in the I-95 corridor near Route 3 and Route 17, as well as reducing crashes, gridlock and a failing level of service for motorists.

VDOT's recommendations were delivered at the December 4, 2013 Commonwealth Transportation Board meeting. 

Study Documents

Fredericksburg Area Congestion Relief Study: Commonwealth Transportation Board Presentation

 

Fredericksburg Area Congestion Relief Study: Evaluation of Conceptual Alternatives (Technical Information Slides)

 

Technical Report, Fredericksburg Area Congestion Relief Study

 

Frequently Asked Questions

 