95 Express Lanes Fredericksburg Extension to Open Final Access Points December 7-8, 2023

The final access points of the 95 Express Lanes Fredericksburg Extension will open at 10 p.m. on December 7, 2023, ready for northbound rush hour the morning of December 8, 2023. Read the news release to learn more.

95 Express Lanes Fredericksburg Extension Opens Thursday, August 17

A 10-mile extension of the 95 Express Lanes in the Fredericksburg area will open to traffic at 10 p.m. on Thursday, August 17, 2023. 

Two reversible high-occupancy toll lanes have been built from just south of Route 610 (Garrisonville Road) in Stafford to the vicinity of Route 17 (I-95 Exit 133).

Watch driver simulation videos to learn how to enter and exit the new facility. 

Once the lanes are open, southbound Express Lanes travelers will be able to drive an additional 10 miles south in the new facility to the Route 17 area. Exiting Express Lanes travelers can enter local I-95 southbound travel lanes near the Rappahannock River to access the Route 17 or Route 3 interchanges or continue in the I-95 southbound through travel lanes toward Spotsylvania or Richmond.

Northbound I-95 through travelers approaching from the Rappahannock River area will be able to enter Express Lanes using a left ramp entrance near the Route 17 interchange.

Additional new access points to and from the Express Lanes near Marine Corps Base Quantico and Courthouse Road will open in late 2023, and local traffic seeking to enter the northbound Express Lanes from Route 17 will use a new flyover ramp beginning in late 2023. 

For more information, please visit expresslanes.com/95extension

Transurban is leading construction of this design-build project. The design-build contractor is a joint venture between Branch Civil and Flatiron.

New Interstate 95 Southbound Exit 133 Off-Ramp: Opened August 2022

Crews opened a new Interstate 95 southbound off-ramp at the exit 133 (Route 17) interchange in Stafford County in August 2022.

Drivers on I-95 southbound seeking to exit to Route 17 northbound toward Warrenton or Route 17 Business (Warrenton Road) southbound toward Falmouth have started using a new off-ramp. The new off-ramp begins before the decision point between the I-95 southbound local and through lanes, north of the Truslow Road overpass.

Southbound I-95 drivers exiting at this interchange are advised to stay right on I-95 southbound after exit 136 (Centreport Parkway) to access the new off-ramp. Travelers merging onto the exit 133 off-ramp are divided by concrete barrier before the division of local and through lanes.

Once drivers enter the new off-ramp to exit 133, they must exit to either Route 17 northbound or Route 17 Business southbound. They are unable to continue on the local lanes toward exit 130 (Route 3) in Fredericksburg.

If motorists miss the new off-ramp to Route 17, they should continue traveling on the I-95 southbound local lanes across the Rappahannock River to exit 130, where they can exit and then enter I-95 northbound to return to exit 133.

American Legion Road Overpass Replacement and Detour

I-95 overpasses on Truslow Road and American Legion Road in Stafford County were replaced with new overpasses as part of the Express Lanes project. New bridges were built to accommodate construction of two reversible Express Lanes in the I-95 median. 

The new Truslow Road overpass opened to traffic on April 9, 2021.

The American Legion Road overpass opened on Jan. 5, 2023. 

Improve 95 Brochure

Learn more about all of the major projects underway on I-95 in the Fredericksburg area through 2024 to build a better ride. 

Three sound wall barriers will be installed as part of the project, click here for an online map of locations

Improve 95 brochure

Benefits 

The project will:

·        Reduce congestion and accommodate travel demand more efficiently

·        Provide greater reliability of travel times 

·        Expand travel choices by increasing the attractiveness and utility of ridesharing and transit usage, while also providing an option for single- and double-occupant vehicles to bypass congested conditions

Major Milestones 

Public information meetings − March 2017

Public hearings − September 2017

Final NEPA decision − January 2018

Issue Request for Proposals (RFP) − Spring 2018

Design-Build contract award − Fall 2018

Construction begins − July 2019

Truslow Road detour begins for overpass reconstruction − January 2020

Truslow Road overpass completion and road reopening − April 9, 2021

American Legion Road detour begins for overpass reconstruction − January 2020

American Legion Road overpass completion and road reopening − April 9, 2021

95 Express Lanes Fredericksburg Extension Partial Opening (mainline) −  August 2023

95 Express Lanes Fredericksburg Extension Opening Date (all access points open) − Late 2023

Resources

UPC: 110527, 114620, and 112046

State ID: 0095-089-739

Lat/Long: 38.346413, -77.485448

Locality: Prince William and Stafford

Page last modified: Nov. 27, 2023