Coming Soon: Route 1 and Fall Hill Avenue Intersection Improvements

SMART SCALE Dashboard

Cost and schedule ►

Public outreach ►

A project submitted for SMART SCALE funding by the City of Fredericksburg seeks to redesign the intersection of Route 1 and Fall Hill Avenue to reduce congestion and improve traffic flow. 

On Route 1, this project will add a southbound right turn lane and extend the northbound right turn lane. The project also aims to reduce conflict points on Route 1 by extending the raised median along Route 1 and converting a short portion of Amaret Street to a one-way condition. 

On Fall Hill Avenue, the project would provide three lanes on both the eastern and western approaches. 

New crosswalks and pedestrian signal crossing equipment are planned to be included at each leg of the intersection as part of the project. 

Benefits 

The project redesigns the intersection by expanding capacity to reduce congestion and improve traffic flow on Route 1 and Fall Hill Avenue. 

The project also will also provide new sidewalks, crosswalks, and pedestrian signals at the intersection.

Major Milestones 

Design Public Hearing: Tuesday, September 21, 2021, 5-7 p.m. Click on the "public outreach" tab at the right of the page to see meeting materials. 

Right of Way: April 2023

Project advertised for construction: May 2024

Construction begins: Summer 2024

Construction complete: Summer 2025

Resources

Other relevant links:

SMART SCALE Project Application

Major funding source: SMART SCALE

Phase: Proposed

UPC: 115117

State ID: 0001-111-316,C501,P101,R201

Federal ID: NHPP-5111(380)

Lat/Long: 38.314260,-77.474782

Locality: Fredericksburg

Page last modified: March 25, 2023