Recently Completed: Route 30 and Route 360 Intersection Improvement
Construction is complete on a project to improve the Route 30 and Route 360 intersection in King William County.
Work began in July 2020 to expand turn lane capacity to enhance safety and reduce delays at the intersection.
The $1.4 million SMART SCALE project built a dedicated right and left turn lanes for eastbound Route 30 and modified existing turn lanes on Route 360.
On the Route 30 westbound approach, the pavement was re-striped with fresh lane markings to create a left turn lane, through travel lane, and right turn lane.
For pedestrians, the project added crosswalks across Route 30 and Route 360, a pedestrian refuge area on Route 360, and push-button pedestrian crossing signal equipment. Sidewalk was built along the south side of Route 30.
Benefits
- The project is intended to enhance safety and improve the intersection's alignment.
Major Milestones
Construction begins: July 2020
Construction complete: April 2021 (two months ahead of June 2021 scheduled completion)
Resources
Wesley Foor, VDOT Area Construction Engineer
(540) 899-4288
Kelly Hannon, VDOT Communications Manager
(540) 374-3344
Phase: Recently completed
Lat/Long: 37.745139, -77.133236
Locality:
King William