Under Construction: 21st Street North over I-66 Bridge Rehabilitation in Arlington County

Cost and schedule ►


Traffic alerts ►

Public outreach ►

Please note: Construction began in July 2023.

This project is rehabilitating the 21st Street North bridge over I-66 located between the Spout Run Parkway (Exit 72) and eastbound I-66 Route 29 Rosslyn/Key Bridge (Exit 73) interchanges.  The bridge was built in 1980.

The project includes:

  • Resurfacing the concrete bridge deck
  • Closing deck joints
  • Repairing concrete piers and abutments
  • Replacing bearings

The width of the existing lanes and sidewalks on the bridge will remain the same.

During construction:

  • Daytime lane closures may be scheduled along I-66 and 21st Street North
  • Overnight lane closures may be scheduled on I-66
  • When one sidewalk along the bridge is closed, pedestrians will be detoured to the sidewalk on the opposite side
  • The Custis Trail under the bridge will remain open to bicyclists and pedestrians
  • Parking will not be allowed on the bridge or approaches

Starting in mid-2024, 21st Street North will be temporarily reduced to one lane on the bridge and open to northbound traffic only. Further information will be provided closer to the start of the partial bridge closure, which will be in place for several months while work occurs on the bridge deck.

Estimated Costs
Preliminary Engineering - $755,000
Construction - $3.3 million
Total - $4.1 million

This project is financed with federal and state funding, including State of Good Repair funds used for bridges.

Benefits 

This project will improve safety for drivers and pedestrians and extend the overall life of the bridge.

Major Milestones 

Virtual Public Information Meeting - June 2022
Advertise for Construction - March 2023
Award Construction Contract - May 2023
Begin Construction - July 2023
Begin 21st Street Southbound Temporary Closure and Detour - Mid-2024
Final Completion - Late 2024

Resources

Contact Info:

Donald Angerman, CCM
Construction
703-259-3253

Yusaf Masud, P.E.
Construction
703-259-2973

Major funding source: State of Good Repair

Phase: Under Construction

UPC: 118788

State ID: 0066-000-912, B625, P101

Federal ID: STP-5B01 (207), NHPP-5B01 (339)

Lat/Long: 38.897568, -77.085199

Locality: Arlington

Page last modified: Oct. 19, 2023