Under Construction: I-66 Rosslyn Tunnel Rehabilitation in Arlington County
Cost and schedule ►
Public outreach ►
This project is rehabilitating and making improvements to the Rosslyn Tunnel that carries I-66 under North Nash Street, Fort Myer Drive, North Lynn Street and Gateway Park. The tunnel, nearly a fifth of a mile long, opened to traffic in 1983.
Improvements include:
- Removing the existing tunnel ceiling to improve long-term maintenance
- Upgrading electrical systems
- Installing a new fireproofing system
- Repairing steel beams, abutment and pier concrete, and joints
- Cleaning and repairing bearings
- Replacing the tunnel lighting system
The tunnel averages 64,000 vehicles a day.
Estimated Costs
Preliminary Engineering - $2 million
Construction - $35.7 million
Total - $37.7 million
This project is financed with state funding.
Benefits
This project will improve safety and extend the overall life of the tunnel.
Major Milestones
Begin Preliminary Engineering - January 2021
Advertise for Construction - April 2022
Award Construction Contract - July 2022
Begin Construction - September 2022
Final Completion - Mid-2025
Resources
Donald Angerman, CCM
Construction
703-259-3253
Yusaf Masud, P.E.
Construction
703-259-2973
Other relevant links:
Construction Underway News Release - Sept. 2022
Major funding source: State
Phase: Under Construction
UPC: 120311
State ID: 0066-000-921, C501, P101
Lat/Long: 38.898741, -77.072987
Locality:
Arlington