In Design: Compton Road Shared-Use Path in Fairfax County

Cost and schedule ►

Public outreach ►

This project will construct a ten-foot-wide shared-use path along northbound Compton Road (Route 658) from the Bull Run Special Events Center Access Road to just south of the I-66 bridge, and from just north of the I-66 bridge to a connection with the existing Cub Run Trail. The project also includes widening the Compton Road bridge over Cub Run to accommodate the new shared-use path. The portion of the shared-use path under the I-66 bridge is being constructed separately as part of the Transform 66 Outside the Beltway Project.

Estimated Costs
Preliminary Engineering - $1.7 million
Right of Way Acquisition and Utility Relocation - $1.3 million
Construction - $6.3 million
Total - $9.3 million

This project is financed with federal, state and local funds.

Benefits 

This project aims to improve bicyclist and pedestrian safety, accessibility and connectivity to the Cub Run Trail system.

Major Milestones 

Virtual Public Information Meeting - December 2021
Virtual Design Public Hearing - June 2022
Begin Right of Way Acquisition - Early 2024
Begin Construction - Mid-2027

Resources

Contact Info:

Hong "Jenny" Ha, P.E.
Location & Design
703-259-2907

Other relevant links:

Virtual Design Public Hearing VideoPresentation, Comment SheetNews ReleaseAd and Meeting Details - June 2022

Right of Way and Utilities Webpage

Previous Meetings >>

Phase: In Design

UPC: 115604

State ID: 0658-029-461, B652, C501, P101, R201

Federal ID: CMAQ-5B01 (106)

Lat/Long: 38.821031, -77.465777

Locality: Fairfax

Page last modified: Aug. 16, 2023