Under Construction: Franconia Road and Rose Hill Drive Intersection Improvements in Fairfax County
Cost and schedule ►
Public outreach ►
This project is making improvements at the intersection of Franconia Road (Route 644) and Rose Hill Drive.
The improvements include:
- A traffic signal flashing yellow arrow on westbound Franconia Road
- Signalized crosswalk on Franconia Road on the western side of the intersection
- Americans with Disabilities Act (ADA) pedestrian signal and curb ramp upgrades
At the intersection, Franconia Road averages 15,000 vehicles a day and Rose Hill Drive averages 7,800.
Estimated Costs
Preliminary Engineering: $93,000
Right of Way Acquisition and Utility Relocation: $58,000
Construction: $384,000
Total: $534,000
This project is financed with federal and state Highway Safety Improvement Program funding.
Benefits
This project aims to improve safety, traffic flow and pedestrian accessibility.
Major Milestones
Notice of Willingness to Hold Public Hearing - August 2019
Begin Right of Way Acquisition - May 2021
Begin Construction - October 2022
Final Completion - Fall 2023
Resources
Michael Monroe, P.E., PTOE
Traffic Operations
703-259-2612
Nick Dais, P.E., PTOE
Traffic Operations
703-259-2237
Other relevant links:
Notice of Willingness to Hold a Public Hearing - August 2019
Major funding source: Highway Safety Improvement Program
Phase: Under Construction
UPC: 112484
State ID: 0644-029-315, C501, P101, R201
Federal ID: HSIP-5B01 (007), HSIP-5B01 (158), HSIP-TS09 (300)
Lat/Long: 38.786366, -77.121338
Locality:
Fairfax