In Design: I-95 Southbound over Neabsco Creek Bridge Replacement in Prince William County
Cost and schedule ►
This project will replace the southbound I-95 general purpose lanes bridge over Neabsco Creek located between the Dale City Car-Only Safety Rest Area South and Cardinal Drive. A new bridge will be constructed due to the estimated rehabilitation cost exceeding 65% of the estimated replacement cost.
The bridge, which averages 74,000 vehicles a day, was built in 1963, repaired in 1977, widened in 1983, repaired in 1991 and repaired again in 2016. An emergency abutment slope repair was done in 2015.
Estimated Project Costs
Preliminary Engineering - $3.8 million
Right of Way Acquisition and Utility Relocation - $190,000
Construction - $47.4 million
Total - $51.4 million
The project is financed with federal and state funding, including State of Good Repair funds used for bridges.
Benefits
This project will improve safety.
Major Milestones
Begin Preliminary Engineering - September 2022
Begin Right of Way Acquisition - Early 2026
Advertise for Construction - Early 2027
Begin Construction - Mid-2027
Resources
Vicente Valeza, Jr., P.E.
Structure & Bridge
703-259-3256
Angel Tao, P.E.
Preliminary Engineering
703-259-2377
Major funding source: State of Good Repair
Phase: In Design
UPC: 121565
State ID: 0095-076-361, B691, P101, R201
Federal ID: NHPP-0952 (555)
Lat/Long: 38.614198, -77.300866
Locality:
Prince William