Recently Completed: I-395/Route 1 Southbound Exit 8C Bridge Repairs in Arlington County

Cost and schedule ►

Public outreach ►

Please note: This project was completed in October 2023.

This project repaired the southbound I-395/Route 1 Exit 8C bridge that carries southbound Route 1 over the 395 Express Lanes, the northbound I-395 general purpose lanes and northbound Route 110.

The repair work included:

  • Retrofitting and spot painting structural steel
  • Replacing the catcher beam system
  • Reconstructing the deck expansion joint
  • Installing a preformed joint seal 

The bridge was built in 1976 and rehabilitated in 1999. It averages 20,000 vehicles a day.

Estimated Costs
Preliminary Engineering - $1 million
Construction - $3 million
Total - $4 million

The project was financed with federal and state funding. 

Benefits 

This project will improve safety and extend the overall life of the bridge.

Major Milestones 

Begin Preliminary Engineering - January 2021
Begin Construction - December 2022
Final Completion - October 2023

Resources

Contact Info:


Maaz Elhadi
Construction
703-259-2765

Yusaf Masud, P.E.
Construction
703-259-2973

Project Photos

Other relevant links:

Construction Underway News Release - Dec. 2022

Programmatic Categorical Exclusion -
May 2022

Major funding source: Federal

Phase: Recently Completed

UPC: 118400, 121827

State ID: 0001-000-920, B624, P101

Federal ID: NHPP-BR09 (310); BR-5B01 (304)

Lat/Long: 38.866109, -77.050439

Locality: Arlington

x2close
0 / 0
list of Photos
I-395/Route 1 Southbound Exit 8C bridge looking east - 2021
1 / 1
list of Photos
Beginning of the I-395/Route 1 Southbound Exit 8C bridge - 2021

Page last modified: Nov. 27, 2023