Recently Completed: Route 29 Northbound Bicycle and Pedestrian Improvements in Fairfax County
Cost and schedule ►
Public outreach ►
Please note: This project was completed in November 2023.
A ribbon-cutting ceremony was held in November 2023.
We and @fairfaxcounty celebrated bike/ped improvements along Rt 29 in #Merrifield today! The new shared-use path along NB Rt 29 from Vaden Dr to Nutley St links to other trails and improves bike/ped access to the Vienna Metro station. #multimodal
— VDOT Northern VA (@VaDOTNOVA) November 3, 2023
More: https://t.co/3vWgljRpRM pic.twitter.com/L0j7bZ62WL
This project constructed missing segments of the shared-use path along northbound Route 29 (Lee Highway) between Vaden Drive and Nutley Street (Route 243).
The project also extended the Route 29 culvert over a tributary of Accotink Creek just west of Nutley Street to accommodate the shared-use path.
Estimated Costs
Preliminary Engineering - $1.2 million
Right of Way Acquisition and Utility Relocation - $1.2 million
Construction - $1.4 million
Total - $3.8 million
This project was financed with local funding and part of the concession fee provided under the Transform 66 Outside the Beltway Project Comprehensive Agreement.
#Merrifield area bicyclists & pedestrians - enjoy your new shared-use path along NB Rt 29 from Vaden Dr to Nutley St! This project constructed missing path segments and extended a culvert to carry the new path over an Accotink Creek tributary.
— VDOT Northern VA (@VaDOTNOVA) October 6, 2023
More: https://t.co/YXq3jlHWhL pic.twitter.com/PeK2t2vq6c
Benefits
The project aims to improve safety and bicyclist and pedestrian access including to the Vienna Metro station and Towers Park.
Major Milestones
Public Information Meeting - March 2019
First Notice of Willingness to Hold a Public Hearing - May 2019
Second Notice of Willingness to Hold a Public Hearing - June 2019
Notice of de minimis Impact on Towers Park - January 2021
Begin Right of Way Acquisition - September 2021
Advertise for Construction - July 2022
Award Construction Contract - September 2022
Begin Construction - November 2022
Shared-Use Path Open to Bicyclists and Pedestrians - October 2023
Ribbon-Cutting Ceremony - November 2023
Final Completion - November 2023
Resources
Chan Basnayake, P.E., PMP, CCM
Construction
703-259-2947
Oscar Jamilla, DPE, PMP
Construction
703-259-2769
Other relevant links:
Ribbon-Cutting News Release - November 2023
Shared-Use Path Opening News Release - October 2023
Notice of de minimis Impact on Towers Park and Supporting Documentation - January 2021
Programmatic Categorical Exclusion - June 2019
Second Notice of Willingness to Hold a Public Hearing - June 2019
First Notice of Willingness to Hold a Public Hearing - May 2019
Public Information Meeting - March 2019
Title Sheet - October 2018
Major funding source: Transform 66 Outside the Beltway Concession Fee
Phase: Recently Completed
UPC: 113518
State ID: 0029-029-414, C501, D614, P101, R201
Federal ID: NHPP-5A01 (946), NHPP-5B01 (153), NHPP-5B01 (231)
Lat/Long: 38.871861, -77.264436
Locality:
Fairfax