In Design: Sherrow Avenue over Tripps Run Culvert Replacement in the City of Falls Church
Cost and schedule ►
This project will replace the Sherrow Avenue culvert over Tripps Run. The culvert was built in 1980.
Estimated Project Costs
Preliminary Engineering - $600,000
Right of Way Acquisition and Utility Relocation - $1.2 million
Construction - $3.3 million
Total - $5.1 million
This project is financed with federal funding.
Benefits
This project will improve safety.
Major Milestones
Begin Preliminary Engineering - July 2023
Public Information Meeting - To be determined
Design Public Hearing - Late 2024
Begin Right of Way Acquisition - Late 2025
Advertise for Construction - Mid-2026
Begin Construction - Late 2026
Resources
Vicente Valeza, Jr., P.E.
Structure & Bridge
703-259-3256
Minwoo Ha, P.E.
Preliminary Engineering
703-259-2207
Other relevant links:
Major funding source: Federal
Phase: In Design
UPC: 121826
State ID: 0073-110-219, D601, P101, R201
Federal ID: BFP-5B01 (319)
Lat/Long: 38.883390, -77.181769
Locality:
Falls Church