In Design: Sherrow Avenue over Tripps Run Culvert Replacement in the City of Falls Church

Cost and schedule ►

This project will replace the Sherrow Avenue culvert over Tripps Run. The culvert was built in 1980.

Estimated Project Costs

Preliminary Engineering - $600,000
Right of Way Acquisition and Utility Relocation - $1.2 million
Construction - $3.3 million

Total - $5.1 million

This project is financed with federal funding.

Benefits 

This project will improve safety.

Major Milestones 

Begin Preliminary Engineering - July 2023
Public Information Meeting - To be determined
Design Public Hearing - Late 2024
Begin Right of Way Acquisition - Late 2025
Advertise for Construction - Mid-2026
Begin Construction - Late 2026

Resources

Contact Info:

Vicente Valeza, Jr., P.E.
Structure & Bridge
703-259-3256

Minwoo Ha, P.E.
Preliminary Engineering
703-259-2207

Other relevant links:

City of Falls Church Project Webpage

Major funding source: Federal

Phase: In Design

UPC: 121826

State ID: 0073-110-219, D601, P101, R201

Federal ID: BFP-5B01 (319)

Lat/Long: 38.883390, -77.181769

Locality: Falls Church

Page last modified: Nov. 1, 2023