In Design: Richmond Highway Corridor Improvements in Fairfax County

Cost and schedule ►

Public outreach ►

Get project updates ►


View the April 2023 project newsletter.

Explore the project's interactive map.

Richmond Highway Interactive Map

This project along three miles of Richmond Highway (Route 1) is being done in two phases: Jeff Todd Way to just north of Frye Road (Phase 1), and then just north of Frye Road to Sherwood Hall Lane (Phase 2). 

Jeff Todd Way to Just North of Frye Road (Phase 1)

Improvements include:

  • Widening about 1.5 miles of Richmond Highway from four to six lanes
  • Adding separate two-way cycle tracks and ADA accessible sidewalks on both sides of the road
  • Reserving median width to accommodate Fairfax County's future dedicated bus-only lanes
  • Intersection improvements including at Mount Vernon Memorial Highway and at Sacramento Drive
  • Replacing the bridges over Dogue Creek and the North Fork of Dogue Creek

Just North of Frye Road to Sherwood Hall Lane (Phase 2)

Improvements include:

  • Widening about 1.5 miles of Richmond Highway from four to six lanes
  • Adding separate two-way cycle tracks and ADA accessible sidewalks on both sides of the road
  • Reserving median width to accommodate Fairfax County's future dedicated bus-only lanes
  • Intersection improvements including at Radford Avenue, Russell Road and Mount Vernon Highway
  • Realignment of Buckman Road to align with Mohawk Lane
  • Replacing the bridge over Little Hunting Creek 

All pedestrian accommodations will be ADA-compliant, turn lanes will be extended wherever possible to improve safety and capacity, and signals throughout the three-mile Route 1 corridor will also be optimized.

In 2015, the Route 1 Multimodal Alternatives Analysis, sponsored by VDOT, the Department of Rail and Public Transportation, the Office of Intermodal Planning and Investment, as well as Fairfax and Prince William counties, identified improvements needed to best meet the needs of both the community and corridor travelers. Key recommendations included a Bus Rapid Transit system constructed in three phases; long-term, a three-mile extension of the Metro Yellow Line to Hybla Valley, and short-term, widening Route 1 with bicycle and pedestrian facilities. 

For more information visit Fairfax County's site on the county's Bus Rapid Transit (BRT) project and the Embark Richmond Highway initiative. While BRT will not be constructed as part of this project, VDOT and Fairfax County are closely coordinating as both projects move forward. 

The project team continues public outreach and meetings as design progresses. 


Estimated Costs

Preliminary Engineering: $25 million
Right of Way Acquisition and Utility Relocation: $213 million 
Construction: $227 million 
Total: $465 million

The project is financed with federal, state, Northern Virginia Transportation Authority and county funding.

Richmond Highway averages about 47,000 vehicles a day within the project limits.

Benefits 

The project aims to improve safety, reduce congestion, and help increase the community’s multimodal options.

Major Milestones 

First Public Information Meeting - April 2017
Second Public Information Meeting - November 2017
Third Public Information Meeting - April 2018
Fourth Public Information Meeting - October 2018
National Environmental Policy Act (NEPA) Public Hearing - October 2018
Design Public Hearing - March 2019
Revised Environmental Assessment Available - August 2020
Begin Phases 1 and 2 Right of Way Total Acquisitions - April 2021
Begin Phase 1 Right of Way Partial Acquisitions - Mid-2023
Begin Phase 2 Right of Way Partial Acquisitions - Late 2023
Begin Phase 1 Construction - Early 2027
Begin Phase 2 Construction - Late 2027

Resources

Other relevant links:

Delegate Kathy Tran Virtual Town Hall Presentation - February 2023

Mount Vee Manor Homeowners' Association Presentation - February 2023

Mount Vernon Council of Civic Associations Turn Lane Analysis Presentation - February 2023

Transportation Advisory Commission Presentation - November 2022

Engleside and Ray's Mobile Colony English and Spanish Presentation - May 2022

Final Design Highway Traffic Noise Report - February 2022

Delegate Kathy Tran Town Hall Presentation - February 2022

Mount Vernon Council of Civic Associations Presentation - July 2021

Delegate Kathy Tran Virtual Town Hall Presentation - January 2021

Federal Highway Administration Finding of No Significant Impact - October 2020

Revised Environmental Assessment - July 2020

Revised Socioeconomics and Land Use Technical Report - July 2020

Fairfax County Supervisor Rodney Lusk Virtual Town Hall Presentation - July 2020

Updated Design Plan Aerials - May 2020

Jeff Todd Way to Brevard Court and Brevard Court to Sherwood Hall Lane

Harmony Place Presentation - February 2020

English and Spanish

Fairfax County Board of Supervisors Endorsement Letter to VDOT - July 2019

Design Public Hearing - March 2019 (Ad)

Transcript

Meeting Materials:
English, Korean and Spanish

Displays: Welcome, Agenda, Typical Section, Potential Pedestrian Underpass and Calendar Schedule | Sacramento and Cooper Intersection | Highland and Frye Intersections | South County Government Center | Buckman Road and Mount Vernon Highway | NEPA - Potential Impacts and Purpose and Need, Environmental Study Area 1 and Environmental Study Area 2 | Stormwater Management Strategy Typical | Traffic - Existing Traffic Volumes, Future Traffic Volumes and 2045 Intersection Level of Service and Travel Times

Mount Vernon-Lee Chamber of Commerce Presentation - February 2019

Air Quality Analysis - December 2017

Hazardous Materials Assessment - December 2017

Indirect and Cumulative Effects Technical Report - December 2017

Socioeconomics and Land Use Technical Report - December 2017

Natural Resources Technical Report - April 2017

Rare, Threatened and Endangered Species Technical Report - March 2017

VDOT Right of Way Guide: English and Spanish

Previous Meetings >>

Phase: In Design

UPC: 107187; 120800

State ID: 0001-029-205, B617, B618, C501, P101, R201; 0001-029-206, B649, C501, P101, R201

Federal ID: STP-5A01 (686), RSTP-5B01 (178), NHPP-5A27 (906)

Lat/Long: 38.728437, -77.109253

Locality: Fairfax

Page last modified: Oct. 26, 2023