Recently Completed: Louisa - Roundabout at Broad Street Road and Cross County Road
Cost and schedule ►
Traffic alerts ►
Traffic Impacts Complete
The intersection was converted to a single-lane roundabout in Spring 2022. Major traffic impacts are now complete, but drivers should remain aware at the intersection and follow guiding signage when applicable as crews complete final improvements.
Construction will be complete by late fall 2022.
Project Details
The primary purpose of this project is to replace the existing two-way stop controlled intersection of Route 250 (Broad Street Road) and Route 522 (Cross County Road) with a single-lane roundabout.
Benefits
A roundabout has been chosen to improve the safety and efficiency of the intersection.
Roundabouts are safer than traffic signals and conventional stop-controlled intersections because traffic can continually and efficiently flow through the intersection and vehicle operating speeds are lower. Additionally, roundabouts help reduce air pollution and fuel use compared to a signalized intersection due to reduced idling and less acceleration and deceleration.
Major Milestones
Public Information Meeting: February 28, 2017
Design Public Hearing: July 24, 2018
Public comment ends: August 3, 2018
Right of way acquisition: Winter 2018
Begin construction: September 10, 2021
Construction complete: December 23, 2022
Resources
Phase: Under Construction
UPC: 107081
State ID: 0250-037-S63, P101, R201, C501
Lat/Long: 37.775515, -77.896890
Locality:
Louisa