Under Construction: Staunton City - Staunton Crossing Street Extension

Cost and schedule ►


Traffic alerts ►

Public outreach ►

This project will construct a 0.85-mile-long urban road on a new location by extending Crossing Way through the Staunton Crossing development site to Valley Center Drive. The proposed road will be three lanes wide, including a single through lane in each direction and a center turn lane. There will be a 10-foot shared use path along the roadway.

The project will also include a 100-space park-and-ride lot with designated parking for future electric-vehicle charging facilities, and a transit stop with space for a future bus shelter.

The total cost for this project is approximately $8.7 million, which includes $840,000 for preliminary engineering and $7.9 million for construction.

This project received $6,807,589 in SMART SCALE funding from an application submitted by the City of Staunton. The remainder of the funding is covered by local contributions, federal funds and other state funds.

Public Hearing Display Board

Benefits 

The project will provide a new connection between Route 250 (Richmond Avenue) and North Frontier Drive. It will also improve access to transportation options with the inclusion of a park-and-ride lot and a new transit facility.

Major Milestones 

Project Location/Design Approval: Spring 2020

Right of Way: N/A

Construction advertisement: Spring 2022

Resources

Contact Info:

Jamie Robertson, P.E.
540-414-1684

Project Photos

UPC: 111048

State ID: U000-132-350

Lat/Long: 38.136944, -79.035000