VDOT News - Fredericksburg
RELEASE: CONTACT: |
IMMEDIATE Darragh Frye 540-899-4119 Darragh.Frye@VDOT.Virginia.Gov |
FRED-161219 June 8, 2020 |
I-95 WORK ZONES NEAR FREDERICKSBURG THIS WEEK
Overnight travelers may experience delays with overnight lane closures on I-95 starting tonight, June 8, through early Sunday, June 14
FREDERICKSBURG, Va. – Overnight travelers on Interstate 95 may experience delays with work zones this week in the Fredericksburg area starting tonight, June 8 through early Sunday, June 14.
Milling and paving on I-95 will continue near the Exit 140 Diverging Diamond Interchange in Stafford County, as well as various construction activities for the I-95 Southbound Rappahannock River Crossing project and the I-95 Express Lanes Fredericksburg Extension project.
In Caroline County, paving work is underway on I-95 southbound between the Caroline County and Spotsylvania County line to the I-95 Southbound Safety Rest Area in Ladysmith.
Message boards are posted along I-95 to alert motorists to lane closures and possible travel delays ahead.
Weather permitting, the following lane closures have been scheduled:
Monday, June 8 – Tuesday, June 9
I-95 Northbound at Exit 126 (Route 1/Spotsylvania)
- 8 p.m. – 5 a.m. – Single lane closure for mobile operation to paint fresh pavement markings near the interchange
I-95 Northbound at Exit 133 (Route 17)
- 9 p.m. – 10 p.m. – Single lane closure for pavement repair
- 10 p.m. – 4:30 a.m. – Double lane closures
- 4:30 a.m. – All lanes reopen
I-95 Northbound at Exit 140 (Courthouse Road)
- 9 p.m. – 10 p.m. – Single lane closure for milling and paving
- 10 p.m. – 4 a.m. – Double lane closures
- 4 a.m. – 5 a.m. – Single lane closure
- 5 a.m. – All lanes reopen
I-95 Southbound from Exit 130 (Route 3/Fredericksburg) to Exit 118 (Route 606/Thornburg)
- 8 p.m. – 5 a.m. – Single lane closure and mobile operations for painting of fresh pavement markings
I-95 Southbound from Mile Marker 117 to I-95 Southbound Safety Rest Area
- 8 p.m. – 9 p.m. – Single lane closure for mobile operation to install pavement markers p.m. – 5 a.m. – Double lane closures
- 5 a.m. – All lanes reopen
Tuesday, June 9 – Wednesday, June 10
I-95 Southbound at Exit 140 (Courthouse Road)
- 7 p.m. – 8 p.m. – Single lane closure for milling and paving
- 9 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – 8 a.m. – Single lane closure
I-95 Northbound at Exit 133 (Route 17)
- 9 p.m. – 10 p.m. – Single lane closure for pavement repair
- 10 p.m. – 4:30 a.m. – Double lane closures
- 4:30 a.m. – All lanes reopen
I-95 Northbound and Southbound at Exit 148 (Quantico Marine Corps Base), Exit 140 (Courthouse Road) and Exit 133 (Route 17)
- 9 p.m. – 10 a.m. – Single lane closure near each of these interchanges
I-95 Southbound from Exit 130 (Route 3/Fredericksburg) to Exit 118 (Route 606/Thornburg)
- 8 p.m. – 5 a.m. – Single lane closure and mobile operations for painting of fresh pavement markings
I-95 Northbound at Exit 126 (Route 1/Spotsylvania)
- 8 p.m. – 5 a.m. – Single lane closure for mobile operation to paint fresh pavement markings near the interchange
I-95 Southbound from Mile Marker 117 to I-95 Southbound Safety Rest Area
- 8 p.m. – 9 p.m. – Single lane closure for mobile operation to install pavement markers
- 9 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – All lanes reopen
Wednesday, June 10 – Thursday, June 11
I-95 Southbound at Exit 140 (Courthouse Road)
- 7 p.m. – 8 p.m. – Single lane closure for milling and paving
- 9 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – 8 a.m. – Single lane closure
I-95 Northbound at Exit 133 (Route 17)
- 9 p.m. – 10 p.m. – Single lane closure for pavement repair
- 10 p.m. – 4:30 a.m. – Double lane closures
- 4:30 a.m. – All lanes reopen
I-95 Northbound and Southbound at Exit 148 (Quantico Marine Corps Base), Exit 140 (Courthouse Road) and Exit 133 (Route 17)
- 9 p.m. – 10 a.m. – Single lane closure near each of these interchanges
I-95 Southbound from Exit 130 (Route 3/Fredericksburg) to Exit 118 (Route 606/Thornburg)
- 8 p.m. – 5 a.m. – Single lane closure and mobile operations for painting of fresh pavement markings
I-95 Northbound at Exit 126 (Route 1/Spotsylvania)
- 8 p.m. – 5 a.m. – Single lane closure for mobile operation to paint fresh pavement markings near the interchange
Thursday, June 11 – Friday, June 12
I-95 Southbound at Exit 140 (Courthouse Road)
- 7 p.m. – 8 p.m. – Single lane closure for milling and paving
- 9 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – 8 a.m. – Single lane closure
I-95 Northbound and Southbound at Exit 148 (Quantico Marine Corps Base), Exit 140 (Courthouse Road) and Exit 133 (Route 17)
- 9 p.m. – 10 a.m. – Single lane closure near each of these interchanges
I-95 Southbound from Exit 130 (Route 3/Fredericksburg) to Exit 118 (Route 606/Thornburg)
- 8 p.m. – 5 a.m. – Single lane closure and mobile operations for painting of fresh pavement markings
I-95 Northbound at Exit 126 (Route 1/Spotsylvania)
- 8 p.m. – 5 a.m. – Single lane closure for mobile operation to paint fresh pavement markings near the interchange
Friday, June 12 – Saturday, June 13
I-95 Southbound at Exit 140 (Courthouse Road)
- 9 p.m. – 10 p.m. – Single lane closure for milling and paving
- 10 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – 8 a.m. – Single lane closure
I-95 Northbound and Southbound at Exit 148 (Quantico Marine Corps Base), Exit 140 (Courthouse Road) and Exit 133 (Route 17)
- 9 p.m. – 5 a.m. – Single lane closure near each of these interchanges
Saturday, June 6 – Sunday, June 7
I-95 Southbound at Exit 140 (Courthouse Road)
- 9 p.m. – 10 p.m. – Single lane closure for milling and paving
- 10 p.m. – 5 a.m. – Double lane closures
- 5 a.m. – 8 a.m. – Single lane closure
For additional information about the Improve95 projects, please visit www.Improve95.org.
511Virginia
Motorists can find real-time information on lane closures, work zones, traffic and other incidents on 511Virginia.
Download the free mobile 511Virginia app for Apple and Android devices to stay connected, or visit www.511Virginia.org. Motorists also can reach 511Virginia by calling 511 from any phone in Virginia
(END)
VDOT’s 14-county Fredericksburg District includes the counties of Caroline, King George, Spotsylvania and Stafford in the Fredericksburg area; Northumberland, Richmond, Lancaster and Westmoreland counties in the Northern Neck; Essex, Gloucester, King & Queen, King William, Mathews and Middlesex counties in the Middle Peninsula.
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.