BRIEF TRAFFIC STOPS FOR CHATHAM BRIDGE CONSTRUCTION DELIVERIES IN FEBRUARY, MARCH
Traffic near Sophia St. and William St. intersection in Fredericksburg may be stopped for 15-minute intervals during daytime hours as new bridge beams are delivered and unloaded

FREDERICKSBURG, Va. – Trucks delivering new bridge beams for the reconstruction of Chatham Bridge will briefly stop traffic near the Sophia Street and William Street intersection in the City of Fredericksburg on several dates in February and March.

Traffic will be stopped for no more than 15-minute intervals, and for no more than several intervals on each delivery day. All deliveries will occur between 10 a.m. and 4 p.m.

Bridge beams will be delivered on the following dates:

  • Monday, Feb. 22
  • Thursday, Feb. 25
  • Friday, Feb. 26
  • Monday, March 1 – Thursday, March 4 (daily)

Temporary no parking signs will be posted for these dates and times to allow trucks to maneuver into the work zone.

Construction is on schedule to reopen the Route 3 Business bridge over the Rappahannock River to pedestrian and vehicle traffic in October 2021. Periodic single lane closures and construction activities will continue through April 2022, when all work will be complete.

The new bridge will be slightly wider, and will have a pedestrian path separated from traffic.

Learn more about the $23.4 million Chatham Bridge improvement project between Stafford County and Fredericksburg on our project page, and view the work zone construction camera.

(END)

VDOT’s 14-county Fredericksburg District includes the counties of Caroline, King George, Spotsylvania and Stafford in the Fredericksburg area; Northumberland, Richmond, Lancaster and Westmoreland counties in the Northern Neck; Essex, Gloucester, King & Queen, King William, Mathews and Middlesex counties in the Middle Peninsula.



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: May 19, 2023