In Design: Rolling Road Widening - Phase 2 in Fairfax County

Cost and schedule ►

Public outreach ►

Please note: Utility relocation for Phase 2 is now occurring and scheduled to continue well into 2024.

Rolling Road Widening (Phase 2)

Phase 2 of this project will:

  • Widen about a mile and a half of Rolling Road (Route 638) from two lanes to four with a raised median, shared-use path and sidewalk between Viola Street and Kenwood Avenue
  • Construct a new traffic signal at Rolling Road and Greeley Boulevard
  • Upgrade the traffic signal at Rolling Road and Barnack Drive
  • Make access management and stormwater improvements

Within the Phase 2 limits, Rolling Road averages about 19,000 vehicles a day.

Rolling Road and Old Keene Mill Road Intersection Improvements (Phase 1)

Phase 1 (completed in November 2021) of this project:

  • Added a second left-turn lane from northbound Rolling Road to westbound Old Keene Mill Road (Route 644)
  • Added a dedicated right-turn lane from northbound Rolling Road to eastbound Old Keene Mill Road
  • Striped four higher-visibility crosswalks
  • Replaced pedestrian signals with ones that are Americans with Disabilities Act (ADA) compliant and accessible
  • Upgraded the traffic signal to accommodate the new turn lanes
  • Reconstructed the median along Rolling Road just south of Old Keene Mill Road

At the intersection, Rolling Road averages about 19,000 vehicles a day and Old Keene Mill Road averages about 28,000.

Estimated Costs

Preliminary Engineering: $8.5 million
Phase 1 Right of Way Acquisition and Utility Relocation: $902,000
Phase 2 Right of Way Acquisition and Utility Relocation: $22.4 million
Phase 1 Construction: $3.1 million
Phase 2 Construction: $43.5 million

Total: $78.4 million

Phase 2 is financed with federal, state (including Revenue Sharing), Northern Virginia Transportation Authority and local funding. Phase 1 was financed with state and local Revenue Sharing funding.

Benefits 

Phase 2 aims to improve safety, traffic flow and bicyclist/pedestrian mobility and accessibility. Phase 1 aimed to improve safety, traffic flow and pedestrian accessibility.

Major Milestones 

Public Information Meeting - June 2016
Public Information Meeting - November 2017
Categorical Exclusion Reevaluation Document Available - February 2018
Design Public Hearing - February 2018
Begin Phase 1 Right of Way Acquisition - July 2019
Begin Phase 2 Right of Way Acquisition - February 2020
Advertise Phase 1 for Construction - October 2020
Award Phase 1 Construction Contract - December 2020
Begin Phase 1 Construction - February 2021
Phase 1 Intersection Improvements Open - October 2021
Phase 1 Final Completion - November 2021
Begin Phase 2 Utility Relocation - June 2022
Begin Phase 2 Construction - Late 2024

Resources

Contact Info:

Khalil Minhas, P.E., PMP, PTOE
Location & Design
(Phase 2)
703-259-2768

Minwoo Ha, P.E.
Preliminary Engineering
(Phase 2)
703-965-0318

Oscar Jamilla, DPE, PMP
Construction
(Phase 1)
703-259-2769

Chan Basnayake, P.E., PMP, CCM
Construction
(Phase 1)
703-259-2947

Other relevant links:

Old Keene Mill Road Intersection Improvements Opening News Release - October 2021

Preliminary Traffic Management Plans for Rolling Road Widening - August 2019

General Notes, Rolling Road Median Removal and Temporary Pavement Installation from Hunter Village Drive to Kenwood Avenue, Widening of Southbound Rolling Road from Birmingham Lane to Hunter Village Drive and Northbound Rolling Road from Glover Court to Kenwood Avenue, Widening of Northbound Rolling Road from Hunter Village Drive to Glover Court and Southbound Rolling Road from Kenwood Avenue to Birmingham Lane, Rolling Road Median Construction from Hunter Village Drive to Kenwood Avenue and Pedestrian Access

Noise Study - June 2019

Final Report and Appendices: A - CD and E - J

Crosswalk Analysis Report  - August 2018

Categorical Exclusion Reevaluation - 
Feb. 2018 (Ad)

Previous Meetings >>

UPC: 5559, 109814

State ID: 0638-029-156, P104, R204, C504; 0638-029-337, R201, C501

Federal ID: RSTP-5B01 (087), STP-5401 (691); STP-5B01 (073), STP-5B01 (155)

Lat/Long: 38.771279, -77.231865

Locality: Fairfax

Page last modified: Aug. 15, 2023